Page Length: 124

Size: 3613 KB

Format: PDF & Word

5,000.00

CHAPTER 1

INTRODUCTION

1.1 Introduction

Generally, the process of awarding any construction contract is based on acompetitive bidding. Contractors will be invited to submit their bids to the owner whonormally awards the lowest bid to construct the project. Beforehand, both the ownerand contractor have to access the construction cost of the proposed project. This isachieved through a construction cost estimate. Although, the actual total cost ofconstruction is not known until the completion of the project, conceptual estimates canbe a good start for the owner and contractor. The owner will be able to estimate inadvance a range of the final cost, to secure the lowest cost to construct the project, and budget the necessary fund in advance. Considering an adequate contingency percentage to the total estimated cost covers such risk. In order to win the contract, the contractor bid price has to be low enough to compete with other competitors, yet high enough to cover his risks and make some profit. Consequently the importance of cost estimates is enormous for all project phase, moreover at the conceptual and feasibility phase.

The preparation of any type of cost estimate depends on the experience of the estimator, the tools used, the time spent, and the information available. Usually the preparation of an estimate starts by breaking down the project into components, then taking off the quantities of the elements of each package and next pricing them all.

Finally, by summing up the price the direct construction cost is computed. This process is long and complex but the most complicated part of it is the quantity take off.

Consequently, computers are considered to be effective tools in cost estimating. due to their capability of doing complex calculation and storing huge amount of data for future use. Any decision concerning the construction of a project that has been or to be executed is based on one type of estimates, which are preliminary estimates, which their moderate level of accuracy owner, quantity survey and contractor consider them as the first choice estimates because they are inexpensive and fast to generate. Owner uses them to decide whether constructing a project is feasible and to evaluate contractors bids, while architect to design within owner’s budget and considering alternatives, and the contractor to know if bidding on a project is profitable or not. Consequently, in the proposed methodology the concentration is on preliminary construction cost estimates with the emphasis on a computer as an avail tool for estimators.

 

1.2 Background

Computers are expending increasingly into all aspects of daily life. The cheaper computer hardware today has boasted the rush of using the computers. Although the move had been slow compared to the others, the construction industry is steadily coping itself with the advancement in the information technology system. As a result, the professional Architects, Engineers and surveyors had computerised their works, and the contractor had started to use computers for their daily business purposes. From a survey by Mohd Hisham Ariffin (2002), it is concluded that the Construction Industry Development Board (CIDB) G7-graded contractors were highly dependent on computer for the administration work while having mediocre dependency on computer for technical work which include scheduling, technical calculation, budgeting, estimating, and others.

The early uses of computers by construction companies were limited to accounting functions. With the advances in micro-computing, increased knowledge of computer capabilities, and the development of user-friendly software, computers have been used everyday construction to make quick and accurate decisions.

The method of pre-tender price estimating have been developed as manual processes. The computer can be used in conjunction with any methods of estimating for the rapid retrieval of cost data, of for calculating an approximate estimating. The advantage of using a computer is that an estimate, however detailed, can be updatedquickly and efficiently for changes, which may be necessary in a revised design.

The computers potential in construction estimating has progressed from its use as an adding machine to an integrated process of computer-aided design (CAD), estimating software, job costing software and project scheduling systems. However the actual use of the computer for estimating is varied within the industry. Some companies use the computer for all projects and with high degree of sophistication.

There is a variety of estimating software program available. Some simplyperform the mathematics of the estimating process, others integrate the estimating operation with other functions of the construction process. No matter how sophisticated the program might be, it is imperative that the estimator understands the calculationmethods and assumptions used in the program. The estimator should be properlytrained and should know all assumptions before proceeding with an estimate.

Computer estimating still involves the measurement of dimensions and compiling materials. This information can then be fed to the computer to obtain the labour, equipment and material costs that may be used to compile the estimate. To perform this type of function, the computer must be programmed to proceed through the required steps, and appropriate unit costs must be stored in it.

An estimator must assemble a large amount of information in an organized manner and perform numerous calculations to prepare a cost estimate. The computer can be used by the estimator to organize, store and retrieve information and to perform the many calculations necessary to prepare an estimate. It can be an effective tool fordecreasing the preparation time and increasing the accuracy of cost estimating.

Numerous computer database can be developed to automate and standardize the estimating function. Historical cost database can be developed from the cost records of projects that have been completed by the company. Information from the historical cost database can be retrieved for the preparation of estimates for future projects. As new information is obtained from current projects, the historical cost database can be updated.

The advent of the relatively powerful and economical computer technology has realistically made the computer-aided estimating become feasible. The number of estimating products increased rapidly since the entry of an interactive computing system into the market. Accompanied with the emergence of estimating software, advance in the database management system has significantly influenced the development of a computer-aided estimating software. Therefore, it can be concluded that the entry ofcomputer technology in the estimating practice is a major event in the improvement of the traditional estimating method by shortening estimate preparation time, reducing the amount of paperwork required for the conventional data storage, improving the quality of documentation. These advantages allow the estimator to pay more attention on decision making during the process of estimation and leave all burdens of data handling tasks to the automated system (Charoenngam, 1996).

 

1.3 Problem Statement

In general, it can be stated that the current estimating programs are unable to fully satisfy their own users. The available software are under–utilized due to its inefficiency in terms of difficulty, cost and because the program does not match with the company’s style of estimate (Charoenngam, 1996). There is very long learningcurve for practicing estimators to operate the system especially for small companies( Lowe,1994).

Most estimating products focus on program manipulation and offer to much irrelevant optional features rather to concentrate on the core estimate preparation. The estimating method and techniques are different from regions, countries to countries, location to locations and companies to companies (Lowe 1994).

Therefore the research is needed because in Malaysia the use of Cost Estimating system was very limited. The most common and widespread method for taking-off was still the traditional method and spreadsheet method. In the mean time, although most of the contractors have their highly capable Cost Estimating system, there are still many of them who still use the spreadsheets program. The reason is that spreadsheet programs actually save more time than the Cost Estimating production system. For all this spreadsheet users, template or standard sheets were being developed to help out Cost Estimating process. The users will only have a key in thedimension and then, they will have quantities for multiple items in one single sheet.

 

1.4 Aim and Objectives ofthe Study

The aim of this project is to develop a prototype computer – aided project cost estimating system which can help the users to prepare preliminary estimate cost of building works. In order to achieve the above aim, the following objectives of study have to be carried out.

  1. To study the various conventional methods of estimating from contractors perspective.
  2. To identify the software used by contractor for cost estimating in practice and the problems they faced in using the software.
  3. To develop a computer – aided project cost estimating system by using Microsoft Access 2003.

 

1.5 Scope of Research

This study only covers the following scopes :-

  1. This study concentrates on developing an application from taking off to automatic approximate cost estimating.
  2. This study concentrates on building work only.
  3. This study focused only on an assortment of contractors who has registered with Pusat Khidmat Kontraktor (PKK) and Construction Industrial Development Board ( CIDB) in Johor Bahru.

 

1.6 Importance ofthe Study

Although it is a simple application, which covers only the approximate cost estimating preparation process, it is a landmark application that cost estimate can be prepared automatically using Microsoft Access. This application will have the samecapabilities with the expensive Cost Estimating production software in terms of preparing Cost Estimate.

As this application only requires Microsoft Access 2003 to run, the cost of obtaining and installing this application is thought to be much cheaper then the available Cost Estimate Production software. As a low cost solution, this will give the contractor much more opportunity to use the computer in preparing their cost estimate.

As a result of this widespread usage, files can be shared among all the parties involved.

 

1.7 Research Approach

The idea of this research initiate from the researcher experience in using KAPPA-PCT Application Development System version

 

2.2 In doing preliminary

Estimate before architectural drawings can be produced. The prototype is developed in the form it is easy to understand and use. The user has to answer the questions appear on the screen such as type of school, location, year when the school is to be build, site condition and piling requirement, that is before the preliminary estimate can be calculated. They cannot accommodate detailed element for preparation cost estimate.

Therefore, the first phase in doing this research is to make study on the Microsoft Access of whether it can be developed into a Cost Estimate Production application.

The second phase involves doing literature review on the Cost Estimate Production software or associated software available in the market. All the software was extensively being reviewed and it form a model for the proposed application.

The third phase is on learning to do programming in Microsoft Access. This is important because this application will be programmed by the researchers who have little experience in programming beforehand.

DOWNLOAD COMPLETE WORK

DISCLAIMER: All project works, files and documents posted on this website, eProjectTopics.com are the property/copyright of their respective owners. They are for research reference/guidance purposes only and some of the works may be crowd-sourced. Please don’t submit someone’s work as your own to avoid plagiarism and its consequences. Use it as a reference/citation/guidance purpose only and not copy the work word for word (verbatim). The paper should be used as a guide or framework for your own paper. The contents of this paper should be able to help you in generating new ideas and thoughts for your own study. eProjectTopics.com is a repository of research works where works are uploaded for research guidance. Our aim of providing this work is to help you eradicate the stress of going from one school library to another in search of research materials. This is a legal service because all tertiary institutions permit their students to read previous works, projects, books, articles, journals or papers while developing their own works. This is where the need for literature review comes in. “What a good artist understands is that nothing comes from nowhere. The paid subscription on eProjectTopics.com is a means by which the website is maintained to support Open Education. If you see your work posted here by any means, and you want it to be removed/credited, please contact us with the web address link to the work. We will reply to and honour every request. Please notice it may take up to 24 – 48 hours to process your request.

WeCreativez WhatsApp Support
Administrator (Online)
Hello and welcome. I am online and ready to help you via WhatsApp chat. Let me know if you need my assistance.