Page Length: 51

Size: 958 KB

Format: PDF & Word

5,000.00

ABSTRACT
This research is focused on the difficulties that gas producers usually face with Hydrate
formation during transportation. Hydrate build up in gas transportation flowlines is one of the
major tasks for gas operators to deal with as it may cease gas flow through the pipeline,
reduce well head measured flow rate, equipment damages e.t.c Two kinds of Engineering
designs were developed to help transport gases of different pressures to an extension facility
whose inlet pressures was designed at 8 barg. HYSYS VERSION 2006 was used for the
simulation of these designs to check for the possibilities of Hydrate formation and
recommendations were made based on the outputs.
Flow velocity is a very important criterion in determining the possibilities of noise in a gas
transporting pipeline. There is a possibility of noise in a gas pipeline if the fluid mean
velocity exceeds 60 ft/sec. Also, one of the objectives of this project is to verify the suitability
of pipe lines sizes for the 8 barg pressure to transport gas over a distance of 120 km. For this
project, a default pipe line size of 10” SCH 40 was selected and other pipe sizes lesser and
greater than it were also used to pick the most suitable, simultaneously considering cost.
PIPESIM VERSION 2009.1 was used for these analyses and the best pipeline size was
determined.
The simulations reveal that both designs are efficient enough and at standard conditions, there
will be no possibilities of hydrate formations but the possibilities of establishing design A
will be recommended because it entails lower cost and less space is required. Also, a pipeline
size of 10” SCH 40 will be sufficient for the given flow conditions but a pipe line size of 8”
SCH 40 can also be used.

vi
TABLE OF CONTENTS
CERTIFICATION ii
DEDICATION iii
ACKNOWLEDGEMENT iv
ABSTRACT v
LIST OF TABLES viii
LIST OF FIGURES ix
CHAPTER ONE 1
1.0 INTRODUCTION 1
1.1 Background Knowledge 2
1.2 Aims and Objectives of the Project 3
1.3 Justification 3
1.4 Scope of work 4
1.5 Problem Statement 4
1.6 Facilities Schematics 5
CHAPTER TWO 7
2.0 LITERATURE REVIEW 7
2.1 Natural Gas Transportation through Pipelines 7
2.2 Single Phase Pipe Flow 8
2.2.1 General Pressure Drop Equations in Gas Flow 8
2.2.2 Simplified Equation 9
2.2.4 Panhandle Equation 11
2.2.5 The Spitzglass Equation 12
2.3 Flow Assurance 12
2.4 Natural Gas Hydrates 14
2.4.1 History of Natural Gas Hydrates 14
2.4.2 Structure of Natural Gas Hydrate 15
2.5 Flow Assurance Challenges and Control 18
CHAPTER THREE 21
3.0 METHODOLOGY 21
3.1 System Description and Simulation Model 21
3.2 Basis of Design 23
3.2.1 Design Basis Feed Composition 23
3.2.2 Basis of Analysis 24
3.2.3 Bulkline 24
vii
3.2.4 Pipeline Hydraulic Profile 24
3.3 HYSYS Simulation Modelling 24
3.3.1 Hysys Compositional Modelling 25
3.4 PIPESIM Simulation Modelling 25
3.4.1 Pipesim Compositional Modelling 26
3.5 Pipe Flow Models and Flowsheets 27
CHAPTER FOUR 30
4.0 Analysis of Results 30
4.1 Results achieved with the HYSYS simulation 30
4.1.1 HYSYS simulation results for design A 30
4.1.2 HYSYS simulation results for design B 33
4.1.3 Comparison of Designs A and B from HYSYS Outputs 35
4.2 Results achieved with the PIPESIM simulation 36
4.2.1 Suitability of pipe various pipe sizes 36
4.2.2 Outlet pressure analysis for design A & B 37
4.2.3 Fluid Mean Velocity for 10 inches sch 40 pipe size 38
4.2.4 Fluid Mean Velocity for 8 and 24 inches sch 40 pipe size 39
5.0 CONCLUSION AND RECOMMENDATION 41
5.1 Conclusion 41
5.2 Recommendation 43
REFERENCES 44
viii
LIST OF TABLES
Table 1: Pressure, Temperature and Flowrates of Natural gas from oil facilities. _________23
Table 2: Compositions of Natural Gas from oil facilities (Dry Base) __________________23
Table 3: Compositions for HYSYS simulation for designs A and B ___________________28
Table 4: Material stream output for Design B in HYSYS simulation __________________29
Table 5: Material stream output for Design A in HYSYS simulation__________________29
Table 6: Output data for stream TO FACILITY B_________________________________31
Table 7: HYSYS presentation of hydrate prediction for the streams in design A_________32
Table 8: HYSYS presentation of hydrate prediction for the streams in design B_________34
Table 9: Pipe sizes variation with corresponding outlet pressures and total distances _____36
ix
LIST OF FIGURES
Figure 1.1: Flow lines from the various well heads to the facility B (Design A)………………….5
Figure 1.2: Flow lines from the various well heads to the facility B (Design B)…………………6
Figure 1.3: Facility schematic showing the flow line from the facility B to the End station…..6
Figure 2.1: Schematics of Structure I, II, and H Gas Hydrates (FEESA 2011)…………………16
Figure 3.0: Flow lines from the various well heads to the facility B (Design A)……………….21
Figure 3.1: Flow lines from the various well heads to the facility B (Design B)………………..22
Figure 3.2: Flow line from the facility B to the End station…………………………………………22
Figure 3.3: HYSYS simulation for design A…………………………………………………………..27
Figure 3.4: HYSYS simulation for design B…………………………………………………………….27
Figure 3.5: Pipesim pipe flow model for 10” SCH 40 pipe size……………………………………..27
Figure 4.0: HYSYS simulation for design A……………………………………………………………30
Figure 4.1: HYSYS simulation for design B……………………………………………………………33
Figure 4.2: Variation of pipe sizes (inches) with total distance (km)……………………………..37
Figure 4.3: Variation of pipe sizes with outlet pressure at facility A……………………………….37
Figure 4.4 Variation of pipe sizes with outlet pressure at facility B………………………………..38
Figure 4.5: A graph of Fluid Mean Velocity (ft/s) DA & DB vs Total Distance (km)…………38
Figure 4.6: A graph of Fluid Mean Velocity (ft/s) DA & DB vs Total Distance (km) for 8”
pipe size………………………………………………………………………………………………………..39
Figure 4.7: A graph of Fluid Mean Velocity (ft/s) DA and DB vs Total Distance (km) for 24”
pipe size………………………………………………………………………………………………………..40
1
CHAPTER ONE
1.0 INTRODUCTION
Flow assurance is relatively a new term in the oil and gas industry. The increase in demand
for energy has seen the industry moving into more challenging environment (offshore and
ultra-deep water) due to the depletion of the conventional onshore (refining and marketing of
crude oil and its products) and shallow water sources of hydrocarbon. Offshore and ultradeep water exploration and production is now going from deepwater (3000 – 6000 ft) towards
ultra-deep water (6000 – 10,000 ft).
The subsea environment which involves low temperatures as well as high pressures, high
water cut and longer transfer periods provides conditions that are ideal for gas hydrates
formation, wax and asphaltene formation, scale and naphthene formation, and other solid
deposits. These are the fundamental obstacles to the production of oil and gas through a long
distance subsea pipelines especially at shut-down and re-start situations.
Though, the existing onshore and subsea processing and transportation facilities enable this
exploitation, but adequate flow assurance is needed. Pipelines, among other means of
transporting oil and gas guarantees delivery from the well head to the processing plants and
from there to the customers.
The movement of gases through pipelines at different velocities comes with different issues
which will be addressed in this research. Some of the problems that occur within the
separation and transportations systems include scaling, oil in water, damage to vessel
internals, residence times, slugging, emulsions, forms, deposit build up e.t.c. Natural gas
hydrates are cage-like crystalline compounds in which a large amount of methane is trapped
2
within a crystal structure of water, forming solids at low temperature and high pressure.
Natural gas hydrates are widely distributed in permafrost regions and offshore.
The purpose of this project is to develop an Engineering design to ensure flow assurance and
simulation for a single phase gas transportation pipeline. One of the major problems in gas
pipelines is noise. For a single phase gas lines, velocity may be a problem if its exceed 60
feet/second (API RP 14E, 1991). Other criteria such as slug formation, flow pattern,
temperature and pressure drop must be carefully analysed to get an effective flow assurance.
1.1 Background Knowledge
Gas hydrates are clathrate physical compounds, in which molecules of gas are occluded in
crystalline cells, consisting of water molecules retained by the energy of hydrogen bonds.
Gas hydrates can be stable over a wide range of pressures and temperatures. All gases can
form hydrates under different pressure and temperature. The crystalline structure of solid gas
hydrate crystals has a strong dependence on gas composition, pressure and temperature.
Presently, three crystalline structures are known for moderate pressure and nearly ten
structures in the pressure range above 100Mpa. Formation of gas hydrates occur when water
and natural gas are present at low temperature and high pressures. Such condition often exists
in oil and gas wells and pipelines. Hydrates plugs can damage equipment of gas transport
system (Yuri F, 2008).
Transportation of natural gas is a very important aspect of the oil and gas industry and as
such, it must be done with much efficiency. Pipelines have been recognized as the most
economic, effective and safest way of transporting natural gas. A lot of capital is needed, due
to cost of pipeline, compressor stations and also in its maintenance.
Pipeline transportation has become an important means of moving natural gas and with the
expansion of market and large demand; millions of pipeline have been laid. Therefore, the
3
process of moving large quantity of this fuel from the gathering station to the refinery the
transportation and distribution by companies to the consumers can be moved through
pipeline. Hence, minimising cost pipeline is necessary but also a pipeline design that will
minimise all possible problems of flow assurance.
1.2 Aims and Objectives of the Project
The aim of the project is to carry out a Flow assurance analysis for a single phase gas
pipeline. It is directed towards the following objectives:
(i) To develop engineering schematic of the gas transporting plant.
(ii) To determine outlet pressure of facility B.
(iii) To design verification of Flowlines from facility B to end station.
1.3 Justification
Natural gas hydrates are crystalline compounds which when formed in oil and gas pipelines,
they may block the pipelines, facilities and equipment, they can cause flow and pressure
monitoring errors, reduction in gas transportation volume, increasing pipeline pressure
differences.
In addition to the precipitation and deposition of solids, the flow assurance faces other
obstacles. For example, if the natural gas is associated with oil, it is necessary to ensure oil
production before exploiting gas. In the specific case of heavy oil, production and
transportation are very challenging because oil viscosity is very high.
Flow velocity is a very essential parameter in gas transportation through pipelines. A flow
velocity for a single phase gas line must not exceed 60 feet/second hence there will be
problems of noise. Noise is highly undesirable in gas transportation. This research needs to be
4
carried out to ensure a proper pipe size suitable for this facility which will keep the flow
velocity within the limit of 0-60 feet/second.
Gases are very volatile and highly explosive. They move at very high pressures and
temperatures and a sudden back flow can lead to loss of lives and properties. Properties here
could be very expensive equipment such as separators, compressors etc. hence, this research
will ensure that any issue of gas back flow will be emitted by carrying out a detailed
simulation.
1.4 Scope of work
AutoCAD 2013 version will be used to develop facility schematics. Facility A will comprise
of the three pressure separators, compressors and coolers. It will also consist of the manifold
for which the gases from the different pressure separators will be joined. The facility B will
comprise of the bulk line which is to transport the compressed gas over a distance of 120 km.
HYSYS as an advance process simulation environment for the process industries developed
by Hyprotech. It is a powerful tool that offers conceptual design, steady state design, dynamic
and real time design (Vaughan, 2000). ASPEN HYSYS V2006 will be used to carry out the
engineering simulation in facility A and the major aim to get an outlet pressure of 83 barg
(which is the inlet pressure of facility B).
PIPESIM V2009.1 will be used to carry out the simulation and hydraulic analysis of facility
B. Its outputs parameters such as flow velocity, slugging etc. will be utilised to carry out an
effective analysis.
1.5 Problem Statement
GLOBAL OIL is an expanding and indigenous company which since its inception in 1994
has been duly responsible for providing quality services. There are currently three gas wells
in field A. As part of the plans to increase her production, the company is planning to drill the
5
gas wells. It was concluded that the wells will be flowing at different pressures and this has
been classified as low pressure, intermediate pressure and high pressure.
An engineering design is required to combine these different pressures at a common manifold
without any problems of pressure backflow to ensure flow assurance so as to prevent any
hazardous occurrence. The inlet pressure at the facility B has been designed as 83 barg.
Hence, a simulation is also required to give an outlet pressure of 83 barg so as to suite what
facility B has been designed for. At Facility B, Global Oil intends to determine the viability
of 83 barg pressure in to transporting the gas through a distance of 120 km for a 10” pipe
(schedule 40).
Other questions to be answered include:
(1) Is the proposed pipeline size cost effective?
(2) What are the possibilities of gas hydrate formation, slug formation and erosion?
1.6 Facilities Schematics
Figure 1.1: Flow lines from the various well heads to the facility B (Design A).
6
Figure 1.2: Flow lines from the various well heads to the facility B (Design B).
Figure 1.3: Facility schematic showing the flow line from the facility B to the End station.

DOWNLOAD COMPLETE WORK

DISCLAIMER: All project works, files and documents posted on this website, eProjectTopics.com are the property/copyright of their respective owners. They are for research reference/guidance purposes only and some of the works may be crowd-sourced. Please don’t submit someone’s work as your own to avoid plagiarism and its consequences. Use it as a reference/citation/guidance purpose only and not copy the work word for word (verbatim). The paper should be used as a guide or framework for your own paper. The contents of this paper should be able to help you in generating new ideas and thoughts for your own study. eProjectTopics.com is a repository of research works where works are uploaded for research guidance. Our aim of providing this work is to help you eradicate the stress of going from one school library to another in search of research materials. This is a legal service because all tertiary institutions permit their students to read previous works, projects, books, articles, journals or papers while developing their own works. This is where the need for literature review comes in. “What a good artist understands is that nothing comes from nowhere. The paid subscription on eProjectTopics.com is a means by which the website is maintained to support Open Education. If you see your work posted here by any means, and you want it to be removed/credited, please contact us with the web address link to the work. We will reply to and honour every request. Please notice it may take up to 24 – 48 hours to process your request.

WeCreativez WhatsApp Support
Administrator (Online)
Hello and welcome. I am online and ready to help you via WhatsApp chat. Let me know if you need my assistance.